BIM Execution Plan (BEP): The Two Types, Every Section, and How to Tell If Yours Is Weak

A BIM Execution Plan is the document that sets out how a project will produce, manage and exchange its information. Under ISO 19650 there are two of them, produced at different moments by different parties for different purposes — and the distinction decides whether the document is a promise or a rulebook. This guide covers both types, every section a complete BEP contains, why a BEP copied from a template is a dead document, what it has to say about authority submission in the Gulf, and ten tests that tell you whether yours is actually working.

What Is a BIM Execution Plan?

A BIM Execution Plan (BEP) sets out how the information requirements on a project will be managed and delivered by all the parties involved. It is produced by the supply chain in response to the appointing party’s Exchange Information Requirements, and it details the responsibilities and deliverables of each stakeholder along with the agreed processes for sharing and exchanging information through every stage.

Put simply: the EIR asks, and the BIM Execution Plan answers. The client states what information they need and when; the delivery team states how it will be produced, by whom, to what standard, in what environment, and to what schedule.

The concept predates ISO 19650 — it was defined in the UK’s PAS 1192-2 as a plan prepared by suppliers explaining how the information modelling aspects of a project would be carried out. What ISO 19650 added was structure, and specifically the split into two distinct documents.

The Two Types of BIM Execution Plan

This is the distinction that most discussion of BEPs skips, and it changes what the document is for.

  Pre-appointment BEP Delivery team BEP
ISO 19650-2 reference Clause 5.3.2 Clause 5.4.1
Prepared by The prospective lead appointed party The appointed lead appointed party
When With the tender response After appointment
Purpose Demonstrate proposed approach, capability and capacity Confirm the plan in agreement with each appointed party
Status A proposal A governing document
Agreed with Nobody yet — it is an offer Every appointed party in the delivery team

The pre-appointment BEP

This is the centrepiece of an ISO 19650 tender response, and it is not a formality or a box-ticking exercise. It is where a prospective delivery team demonstrates three things: that they understand the Exchange Information Requirements, that they have the capability and capacity to deliver against them, and that they have a coherent strategy for managing information across the project.

A pre-appointment BEP that reads as a generic capability statement rather than a specific response to this client’s requirements tells the appointing party exactly what they need to know — and it is not flattering.

The delivery team BEP

After appointment, the lead appointed party confirms the delivery team’s BEP in agreement with each appointed party. That phrase carries weight: this is not a document the lead issues and others receive. It is negotiated and agreed, because each task team has to be able to actually do what it commits to.

The journey between the two is the whole point: the BEP goes from a tender promise to the document that governs construction. If the delivery team BEP is simply the pre-appointment BEP with a new date on it, the agreement step never happened.

Responding to an EIR or building a delivery team BEP?

AMC Engineer delivers coordinated LOD 300–500 BIM models across Architecture, Structure, MEP, Electrical, Infrastructure and Landscape — working to your project’s information standards, naming and classification from the first upload. Free LOD 200 sample from your own drawings in 24 hours.

Explore BIM Modeling Services
Request a Free Sample

A BIM Execution Plan Responds to the EIR

The single most useful rule in this subject, and the one that separates a working BEP from an expensive PDF.

Published guidance is explicit: the BEP should reflect and respond to the Exchange Information Requirements, and therefore any section that does not correlate to the information requirements, to the information management processes, or to project-specific information should not be there.

Read that as an instruction and it changes how you write the document. A BEP is not a demonstration of BIM knowledge. It is an answer to a specific set of questions the client asked. Sections that exist because the template had them — a page on the history of BIM, a generic software list, a description of clash detection in the abstract — are not neutral padding. They dilute the document and signal that nobody read the EIR closely.

The practical test. Open the EIR and the BEP side by side. Every requirement in the EIR should have a traceable answer in the BEP. Every section in the BEP should trace back to a requirement, a process or a project-specific fact. Anything in the BEP that traces to neither is a candidate for deletion — and anything in the EIR with no answer is a gap you will be asked about.

Every Section of a BIM Execution Plan

Contents vary with the project and the client, but a complete BIM Execution Plan aligned to ISO 19650-2 covers this ground.

# Section What it establishes
1 Project information Project description, location, intended use, stages covered
2 BIM goals and objectives What the information is for — tied to the client’s stated purposes
3 Delivery team and roles Team structure, task teams, and the information management function schedule
4 Information management processes How information is produced, checked, approved, authorised and delivered
5 Standards and methods Which standards, national guidance and client standards apply, and which prevails
6 Naming and classification Container identifier structure, revision codes, status codes, classification system
7 Common data environment Platform, states, permissions, workflows, hosting and ownership
8 Software, versions and exchange formats Authoring and coordination tools, versions, and native and open formats
9 Level of information need Geometry and data required per element per milestone, per purpose
10 Coordination and clash process Federation strategy, test matrix, tolerances, cadence, issue management
11 Information security Security triage and classification under ISO 19650-5, and incident response
12 Training requirements Per-role training needs and schedule
13 Delivery plan and milestones Per-stage deliverables and dates
14 Structured data delivery COBie or equivalent — version, sheets, validation, responsibility
15 TIDP Task Information Delivery Plan per task team
16 MIDP and appendices Consolidated Master Information Delivery Plan, plus supporting templates

Two sections in that list are routinely missing entirely from BEPs in practice: information security and training. The first matters on government, utility, healthcare and critical infrastructure work. The second matters because a BEP committing a team to a workflow nobody has been trained on is a commitment to a failure.

Roles and the Information Management Function

The BIM Execution Plan names who does what, and ISO 19650 is specific that information management is a function to be performed rather than automatically a job title.

  • Appointing party — the client, who issues the information requirements and authorises information for use.
  • Lead appointed party — typically the lead designer or main contractor, who establishes the BEP and coordinates the delivery team.
  • Appointed parties — each consultant, subcontractor or specialist producing information.
  • Task teams — the working units within appointed parties who produce information containers.

The BEP should include an information management function schedule showing who performs each function, and the delivery team directory showing the hierarchy between task teams. Where a role is named without a named person and a named deputy, it will be unowned within a month.

Standards, Naming and Classification

The BIM Execution Plan fixes the conventions before production starts, because retrofitting them across a completed container set is days of work with no design value.

  • Which standards apply — the ISO 19650 parts, any national guidance, the authority’s submission requirements, and the client or master developer standard.
  • Which prevails on conflict. On Gulf projects a client standard, a municipal submission guide and a national annex can all say different things about naming. The BEP is where that is resolved, in writing, before anyone uploads anything.
  • The container identifier structure — the coded fields and their permitted values.
  • Revision and status codes, with their meanings stated rather than assumed.
  • The classification system, applied consistently across all disciplines.

Our guide to ISO 19650 and BIM standards covers the layered stack of requirements and how to read it.

The CDE and Status Codes

The BEP defines the common data environment: which platform, how the four information states are configured, who has permission at each state, and how information moves between them through approval and authorisation.

Three questions the BEP should answer explicitly, because they cause disputes when left open:

  • Who hosts it, who pays, and for how long after completion.
  • Who owns the data and the intellectual property in the models.
  • What happens at handover and on early termination — export format, archive transfer, continuing access.

Our guide to the common data environment covers the four states, the three gates and the hosting and ownership questions in detail.

Level of Development and Level of Information Need

The BEP states how much information each element must carry at each milestone, and for what purpose.

Two vocabularies are in use and both appear in Gulf projects. The LOD scale from 100 to 500 describes how developed and reliable an element is. Level of Information Need under ISO 19650 is purpose-driven — it asks what the information is for and specifies exactly the geometry and data needed to serve that, and no more.

Whichever the project uses, the BEP should express it as a matrix rather than a single number, because a project-wide “LOD 350” is not a specification. Our guide to BIM levels of development covers what each level supports and where the distinction between 300 and 350 becomes expensive.

Coordination Process and Cadence

The BIM Execution Plan defines how coordination actually runs, and vagueness here produces the most visible failures on site.

  • Federation strategy — which models federate, how often, and who owns the federated file.
  • The clash test matrix, discipline pairs in priority order, with tolerances per pair.
  • Meeting cadence and the model submission day, fixed and published.
  • Issue management — classification, ownership rules, escalation and closure.
  • The movement hierarchy — which system moves when two conflict, so meetings resolve rather than negotiate.
  • Exit criteria — what “coordinated” means and who signs it off.

Our guide to BIM coordination covers the seven-step cycle, the model intake checklist and a workable meeting agenda.

TIDP and MIDP

Two acronyms that appear in every BEP template and are understood in surprisingly few.

  TIDP MIDP
Stands for Task Information Delivery Plan Master Information Delivery Plan
Scope One task team The whole delivery team
Produced by Each task team The lead appointed party, consolidating the TIDPs
Contains Every container that team will deliver, with author, due date and dependencies All TIDPs combined, aligned to project milestones
Answers What am I producing and when? Is the whole information delivery achievable, and where does it conflict?

The value is in the consolidation. Individually, every TIDP looks achievable. Combined into an MIDP, the conflicts appear — two teams depending on the same input on the same date, or a deliverable due before the information it needs exists. That is the point of building it, and it is why an MIDP assembled after the deadlines are already set is a record rather than a plan.

The BIM Execution Plan and Gulf Authority Submission

In most markets a BEP is an internal discipline. In Saudi Arabia and the UAE it increasingly has an external consequence, and this is the section most published BEP guidance omits entirely.

Dubai

Dubai Municipality has required BIM on defined categories of project since 2013, and a circular issued in October 2023 introduced BIM model submission for new building permits with IFC as the format, taking effect from the start of 2024. When the model is the submission, the BEP’s decisions about classification, naming, property sets and export configuration stop being internal preferences and become permit conditions.

Abu Dhabi

Abu Dhabi Municipality publishes CAD and BIM submission requirements covering naming conventions, coordinate systems and file formats, with compliance requirements referencing ISO 19650. A separate model quality document addresses naming standards, model coordination and clash detection protocols. That means the coordination process defined in your BEP is being measured against a published expectation, not only against your own standard.

Saudi Arabia

Requirements are predominantly driven by client and programme. Large developers and giga-project programmes routinely specify information requirements and BEPs contractually, and those specifications are frequently more demanding than any municipal requirement.

What the BEP should therefore contain

  • The authority submission requirement named explicitly, with its current edition.
  • The export configuration that satisfies it — IFC version, classification mapping, property sets.
  • An export testing schedule. Test the authority export in the first weeks and at every milestone, not the week before submission.
  • Who owns the submission and who verifies it before it goes.
Verify current requirements before writing the BEP. Submission rules, formats, project categories and thresholds across the Gulf have changed several times and differ by emirate, municipality and project type. Confirm the applicable requirement and its current edition directly with the relevant authority or your client’s information manager rather than relying on any summary, including this one.

Need a delivery team that works to your BEP, not around it?

We work within your information standards — naming, classification, status codes and coordinate systems agreed up front — and issue every model and drawing with status and revision applied.

See How We Work
Talk to Our BIM Team

Software Versions on Multi-Party Projects

An operational decision that belongs in the BEP and is frequently left out until it causes a problem.

Revit file upgrades are one-way. A model saved in a newer version cannot be opened in an older one, with no downgrade path. On a project with five consultants, that single fact makes version alignment a contractual matter rather than an individual preference.

The BEP should state:

  • The software and version every party will use, for the duration.
  • The upgrade protocol — who decides, how much notice, what the cut-over looks like, and who tests add-ins first.
  • The exchange format where versions differ, which is normally IFC and is version-independent.
  • Add-in and script dependencies that must be tested before any upgrade.

Our guide to what’s new in Revit 2027 covers the compatibility problem and an upgrade decision framework in detail.

How to Tell If Your BIM Execution Plan Is Weak

Every BIM Execution Plan looks complete. These ten tests distinguish the ones that govern a project from the ones that sit in a folder.

  1. Can you trace every EIR requirement to an answer in it? If not, the gaps will surface as questions later.
  2. Would deleting the project name make it obviously generic? A BEP that could belong to any project answers no client’s requirements.
  3. Is every role assigned to a named person with a named deputy? Roles assigned to companies are unowned.
  4. Does it state which standard prevails when two conflict? If not, someone will decide that under time pressure, alone.
  5. Is the LOD expressed as a matrix rather than a single number? A project-wide LOD is not a specification.
  6. Does it define what “coordinated” means and who signs it off? Without an exit criterion, coordination ends when the programme says so.
  7. Does the MIDP exist, and was it built before the milestone dates were fixed? Assembled afterwards, it is a record rather than a plan.
  8. Does it name the authority submission requirement and its edition? On Gulf projects, an unnamed submission requirement is an unmanaged risk.
  9. Is there an export testing schedule with dates? Untested exports fail at submission with no time to fix them.
  10. Has every appointed party actually agreed to it? Under ISO 19650-2 the delivery team BEP is confirmed in agreement with each appointed party. A document issued rather than agreed has skipped the step that makes it binding.
The fastest single check. Ask a task team leader who was not involved in writing the BEP what their submission day is and which status code they issue under. If they do not know, the document is not governing the project regardless of how complete it looks.

Seven BIM Execution Plan Failures

Failure What it causes The fix
Generic BEP copied from a template A document answering no client requirement, that nobody uses Respond to the EIR point by point; delete what traces to nothing
Delivery team BEP is the tender BEP re-dated The agreement step never happened; task teams committed to nothing Confirm it in agreement with each appointed party
Conflicting standards unresolved Two naming conventions running in parallel, discovered mid-project State which prevails, in writing, before production
Roles assigned to companies Unowned functions within a month Named person and named deputy for every role
Software versions not fixed One party upgrades; native exchange breaks and cannot be reversed Fix versions and an upgrade protocol in the BEP
Authority submission not addressed Export failures discovered at permit submission with no float Name the requirement and schedule export testing from week one
MIDP assembled after milestones are set A record of an unachievable plan rather than a check on it Consolidate TIDPs before dates are committed

Frequently Asked Questions

What is a BIM Execution Plan?

The document that sets out how a project will produce, manage and exchange its information. It is produced by the supply chain in response to the appointing party’s Exchange Information Requirements, and it details the responsibilities and deliverables of each stakeholder along with the agreed processes for sharing information through every project stage. The EIR asks; the BEP answers.

What is the difference between a pre-appointment BEP and a delivery team BEP?

Under ISO 19650-2, the pre-appointment BEP is established by the prospective lead appointed party and included in the tender response, demonstrating proposed approach, capability and capacity. The delivery team BEP is confirmed after appointment by the lead appointed party, in agreement with each appointed party. The first is a proposal; the second is a governing document.

Who prepares the BIM Execution Plan?

The supply chain, not the client. The prospective lead appointed party prepares the pre-appointment BEP for the tender, and after appointment the lead appointed party confirms the delivery team BEP in agreement with each appointed party. The client’s contribution is the Exchange Information Requirements that the BEP responds to.

What should a BEP contain?

Project information, BIM goals, delivery team and roles, information management processes, standards and methods, naming and classification, the common data environment, software and exchange formats, level of information need, the coordination and clash process, information security, training requirements, the delivery plan and milestones, structured data delivery such as COBie, the TIDPs and the consolidated MIDP.

Why is a generic BEP a problem?

Because guidance is explicit that the BEP should reflect and respond to the Exchange Information Requirements, and any section not correlating to the information requirements, the information management processes or project-specific information should not be there. A BEP that could belong to any project answers no client’s actual requirements, and signals that nobody read the EIR closely.

What is the difference between TIDP and MIDP?

A Task Information Delivery Plan covers one task team, listing every container that team will deliver with author, due date and dependencies. The Master Information Delivery Plan consolidates all TIDPs across the delivery team and aligns them to project milestones. The value is in the consolidation, because individually every TIDP looks achievable and the conflicts only appear when they are combined.

What does the BEP say about the common data environment?

Which platform is used, how the information states are configured, who has permission at each state, and how information moves through approval and authorisation. It should also answer three questions that cause disputes when left open: who hosts it and pays for it and for how long after completion, who owns the data and the intellectual property, and what happens at handover and on early termination.

Should software versions be in the BEP?

Yes, and they often are not. Revit file upgrades are one-way, so a model saved in a newer version cannot be opened in an older one. On a multi-consultant project that makes version alignment contractual rather than a preference. The BEP should fix the software and version for every party, state the upgrade protocol, name the exchange format where versions differ, and identify add-in dependencies to test before any upgrade.

How does the BEP relate to authority submission in the Gulf?

Directly, where the model is the submission. Dubai Municipality introduced BIM model submission in IFC format for new building permits following a circular issued in October 2023, and Abu Dhabi Municipality publishes submission requirements covering naming, coordinate systems and file formats referencing ISO 19650, alongside model quality requirements. The BEP should name the requirement and its edition, define the export configuration that satisfies it, and schedule export testing from the first weeks.

How do I know if my BEP is any good?

Test it: can every EIR requirement be traced to an answer, would deleting the project name make it obviously generic, is every role assigned to a named person and deputy, does it state which standard prevails on conflict, is LOD a matrix rather than one number, does it define what coordinated means and who signs it off, does the MIDP predate the milestone dates, does it name the authority submission requirement, is there an export testing schedule, and has every appointed party actually agreed to it?

What is the fastest way to check a BEP is being used?

Ask a task team leader who was not involved in writing it what their model submission day is and which status code they issue under. If they do not know, the document is not governing the project regardless of how complete it looks on paper.

Is a BEP required by ISO 19650?

The ISO 19650-2 process includes both the pre-appointment BEP and the delivery team BEP as defined steps, so on a project working to ISO 19650 the BEP is part of the process rather than optional. Whether ISO 19650 itself applies to your project is determined by the contract, the client’s requirements or an authority mandate — the standard does not impose itself.

Conclusion

A BIM Execution Plan fails in one of two ways. Either it is generic — a template with a project name on it, answering requirements nobody read. Or it is complete and unagreed — a thorough document the lead party issued and the task teams never committed to.

Both are avoidable with the same discipline: write the BEP as an answer to the EIR, delete anything that traces to neither a requirement nor a project fact, and confirm it in agreement with each appointed party rather than issuing it. On projects in Saudi Arabia and the UAE, add one more section that most guidance omits — name the authority submission requirement, define the export configuration that satisfies it, and schedule the export test for week one rather than the week before you submit.

Let’s get the information plan right before production starts.